Energy infrastructure's at the heart of fleet electrification
When businesses start to electrify their fleets with electric vehicles (EVs) or electric heavy goods vehicles (eHGVs), the focus often falls on choosing vehicles and installing chargers. And while both are essential, electrification touches almost every part of your business, from operations and finance to the people who drive and manage your vehicles.
Energy's one of the biggest parts of the puzzle, because your chargers are only as useful as the power available to run them. And most offices and depots weren't designed to charge vehicles at scale.
How much power you need depends on your fleet. Cars and vans that park overnight may only need slower alternating current (AC) chargers. eHGVs and vehicles with quick turnarounds may need faster direct current (DC) charging. That places far greater demand on your site.
The good news is you don't have to start with a costly upgrade. Start with your data to understand how your fleet runs and what your site can supply. Then you can make the most of the power you've already got, and invest where you need to from there.
Start with your data
Your first step is to understand how your fleet operates and your site’s electrical capacity.
Telematics is the best place to start. It shows your vehicles' routes, daily mileage, schedules and dwell times. From this, you can work out the number and location of chargers you may need, where they’re best located, and the charging power speeds required to support your operation.
Next, look at your site. Every site has a limit on how much electricity it can draw from the grid at any one time. This is your agreed supply capacity, and you'll usually find it on your electricity bill or supply contract.
Your electricity consumption data then shows how much of that capacity you're already using. Where half-hourly consumption data is available, this can provide a much more detailed view of demand patterns across the day. The gap between the two is your 'headroom' - the spare power you've got available for charging.
That headroom changes throughout the day. A busy office might have little to spare at midday but plenty overnight, which is often when your vehicles are parked.
Put the two together and you'll see where charging fits comfortably and where there are gaps. That tells you where you can optimise, and where you may need more power.
A phased rollout can also help you build this picture before you commit to a full fleet. That's how we approached our work with SES Water. We started with 10 vehicles, then expanded as the business case became clear.
Make the most of the power you have
Smart charging's the first tool to reach for when you're optimising. It schedules and controls charging, so each vehicle charges at the right time and speed. If a van's parked for 12 hours, it doesn't need full power the moment it plugs in.
Smart charging builds on the data you've already gathered. You can set rules for when vehicles leave, how much charge they need and which ones get priority. A van heading out at 6 am can charge first, while one that's parked until midday can wait. Most modern chargers have smart features built in, so it's often about setting them up well rather than buying new kit.
Load management works alongside it. It monitors your site's total demand in real time and shares the spare capacity between your chargers. When your building's busy, charging slows. When demand drops, such as overnight, charging speeds up.
This keeps you within your site’s capacity and helps you avoid peaks in energy demand, and the costs associated with this. It also means you can often install more chargers than your headroom alone would suggest, because they won't all draw full power at once.
You can also:
- match charger speeds to dwell times, so you only install fast charging where you need it
- stagger charging across shifts, so vehicles don't all plug in at once
- charge when electricity is cheaper, if your tariff allows
Together, these steps can help you support more vehicles without upgrading straight away.
If optimisation measures aren't enough and a connection upgrade isn't immediately practical, battery energy storage systems (BESS) can help bridge the gap. A battery charges up when your site's demand is low, then releases that electricity at peak times.
Battery storage tends to suit sites with short, sharp peaks, like depots where lots of vehicles return and plug in at once. It's also worth a look where a grid upgrade would be slow or costly, or where you've got on-site solar to store.
The technology's well established and costs have come down in recent years. But it's still a significant investment, and a battery can only supply what it's stored. So it's best weighed up alongside a connection upgrade, rather than treated as a default.
Invest in infrastructure
Optimisation can only take you so far. As your fleet grows, you'll likely need more capacity. And that usually means two kinds of work.
The first is your grid connection. If your site needs more power than your connection allows, you'll apply for an upgrade through your distribution network operator (DNO) or independent distribution network operator (IDNO). The second is on-site electrical work, such as new switchgear, cabling and groundworks to bring power to your chargers.
Every site's different, so the work involved can vary a lot. When we helped car retailer Arnold Clark build its network of 62 ultra-rapid charging hubs, its Leyland Motorstore needed detailed planning and a long cable route to connect the chargers.
Both kinds of work take time and investment (although there are ways to reduce the upfront costs – from government grants to flexible funding options), so it pays to plan earlysooner rather than later. Use the data you gathered at the start to work out what you'll need, and when.
Planning early also lets you think about tomorrow's fleet as well as today's. If you're already digging for groundworks, laying extra ducting for future chargers costs far less than breaking ground again later. And it can be worth sizing your connection for where your fleet's heading, not just where it is now.
Put energy at the start of your plan
Our advice is simple: put energy at the start of your electrification plan, not the end. Bring your energy team together with your fleet, facilities, finance and procurement teams early, and look at your vehicle and site data side by side.
You'll get a clear picture of what your sites can support today and what they'll need tomorrow. Then you can make confident decisions on vehicles, chargers and infrastructure, in the right order.
Want to explore what this could look like for your business? Get in touch.
Get in touchDisclaimer
We’ve used all reasonable efforts to ensure that the content in this article is accurate, current, and complete at the date of publication. However, we make no express or implied representations or warranties regarding its accuracy, currency or completeness. We cannot accept any responsibility (to the extent permitted by law) for any loss arising directly or indirectly from the use of any content in this article, or any action taken in relying upon it.
Subscribe to our newsletter
Sign up to our monthly newsletters and get the best of Drax Insights sent directly to your inbox.